TRENDING
A mountain gorilla looks at the camera from green forest undergrowth
October 29, 2026
How to Compress Time-Series Metrics in Python With Gorilla Delta-of-Delta and XOR Encoding
A bronze-framed hourglass with white sand beside a small Ferris wheel ornament on a wooden table against a teal wall
October 29, 2026
NIST’s Final Post-Quantum Transition Report Puts Every Quantum-Vulnerable Public-Key Scheme on One 2030 and 2035 Clock, and Three Federal Documents Word the Deadline Three Ways
Six weathered stone columns of the Temple of Apollo at Delphi, Greece, standing on a stone platform above a valley of olive groves
October 29, 2026
Honeypots Recorded Probes Against Oracle E-Business Suite CVE-2026-101767 Seven Days After Its Patch, and the Finder’s Write-Up Is Dated Patch Day
Vintage silver stopwatch with a chain on a black background, its dial showing seconds from 5 to 60
October 29, 2026
How to Find a Slow Query in PostgreSQL 18 With pg_stat_statements, Read Its EXPLAIN ANALYZE Plan, and Fix It With the Right Index
A wooden Tower of Hanoi puzzle on a market table, with three pegs and stacked discs of different sizes
October 29, 2026
Two Labs’ Claimed Refutations of the Exponential Time Hypothesis Turn Verification Into a Statement-Reading Problem, and Their Lean Theorems Promise Only That a Constant Exists
29 Oct 2026
SXZ.io SXZ.io
  • Home
Search the Site
Popular Searches:
Technology Amazon AI
Recent Posts
A flock of snow geese in flight, seen as dark silhouettes against an orange and red sunset sky with layered clouds
How to Run Zero-Downtime Schema Migrations on PostgreSQL 18 and Block Unsafe ALTER TABLE Statements With a Python Lint Gate
October 28, 2026
An old green steel truss bridge resting on temporary supports beside a new arch bridge under completion on a river in Portland, Oregon
The Angular 2 Rewrite Turns a Migration Lesson Into a Security Bill: AngularJS Still Draws 533,480 Downloads a Week, and 10 Advisories Have No Open-Source Fix
October 28, 2026
Hundreds of yellow rubber ducks floating in a river enclosure during a duck race
WordPress 7.1.4 Closes an Unauthenticated Race in Its Own Update Routine, but 19 Older Branches Had No Backport Hours After Release
October 28, 2026
SXZ.io SXZ.io
  • Home

Categories

Articles 270 Posts
News 273 Posts
Learning Hub 243 Posts
Home/News/3 Gigawatts of Data Centers Dropped Off the PJM Grid After a Power Line Failed
News

3 Gigawatts of Data Centers Dropped Off the PJM Grid After a Power Line Failed

A downed transmission line near Washington, D.C., triggered more than 3 gigawatts of data center load to drop off the PJM grid in seconds, sending a voltage disturbance from Northern Virginia to...

July 25, 2026 4 Min Read
59

A single transmission line failure outside Washington, D.C., on the morning of July 22 set off a cascade that pulled more than 3 gigawatts of data center load off the largest power grid in the United States, sending a voltage disturbance that was felt from Northern Virginia to Chicago. There was no blackout, but as TechCrunch reported, the incident is a stark example of how the AI data center boom can stress grid stability faster than operators adapt.

Table Of Content

  • How a Routine Line Fault Became a Regional Event
  • “The Canary in the Coal Mine”
  • Two Ways to Fix It
  • A Near Miss With a Warning Attached

The event hit the PJM Interconnection, the grid operator whose territory stretches from New Jersey to Illinois and serves 67 million customers. Reuters reported that roughly 3 percent of the grid’s total demand vanished in seconds, and PJM registered both the sudden drop and a shift in grid frequency, the measure of how closely electricity supply and demand are matched. A downed line is normally a non-event that the grid corrects within seconds. This time it took more than 10 minutes to stabilize.

How a Routine Line Fault Became a Regional Event

When the line went out of service, data centers in Northern Virginia, home to the world’s largest concentration of them, sensed the resulting voltage dip and did exactly what they are built to do: they switched to backup power. That decision was made by the data centers’ own control systems rather than by any grid operator, Dominion Energy, the regional utility, said in a statement.

That self-protective reflex is the core problem. As each facility shed its load almost simultaneously, TechCrunch reported that about 3.1 gigawatts disappeared in roughly 30 seconds. The grid partially recovered, then a second wave of load fell away. At its peak, PJM was left carrying an extra 3.49 gigawatts with nowhere to send it, which pushed voltages up and made light bulbs flicker across the region before the system was brought back into balance.

The grid runs on a near-perfect match between supply and demand, so when a large block of demand disappears at once, supply surges and voltage spikes. Those swings can trip failsafes that force still more equipment offline. Bob Marshall, chief executive of Ting Labs, whose network of 1.4 million socket-level sensors recorded the disturbance across the eastern United States, called it “a massive event” and said customers reported flickering lights and noises from their air conditioners and refrigerators. Grid wobbles are usually corrected in milliseconds, he noted; this one lasted about 10 minutes.

“The Canary in the Coal Mine”

Experts describe the event as a preview rather than an anomaly. “It’s the canary in the coal mine,” Ricardo de Azevedo, chief technology officer at ON.Energy, told TechCrunch, adding that these large-load disruptions are “happening more and more.” The disturbance echoed a 2024 event on the same PJM grid, when roughly 60 data centers disconnected at once and pulled 1.5 gigawatts offline. This week’s drop was about twice as large.

The trend line is steep. Data centers accounted for about 6 percent of PJM’s load in 2024, according to Synapse Energy Economics, and that share keeps climbing as AI training and inference workloads expand. DataCenterDynamics noted that PJM is already staring at an unprecedented power shortfall over the coming decade driven by data center demand, a gap between new load and new generation that PJM has warned could pressure grid reliability later this decade.

Two Ways to Fix It

The proposed fixes fall into two categories: coordinate how data centers leave and rejoin the grid, and build them to ride through disturbances instead of fleeing them.

The coordination challenge is synchronization. “We need to figure a way for these loads that are located next to each other to sequentially either disconnect or reconnect,” said Ali Zain Banatwala, a senior market models specialist at the Independent Electricity System Operator, Ontario’s grid operator. Staggering those transitions would give operators room to plan procedures in advance rather than absorbing thousands of megawatts vanishing in a single breath.

On the hardware side, ON.Energy offers a campus-scale uninterruptible power supply that covers not just servers but chillers and other equipment. The system parks the entire data center behind a bank of batteries and power conversion gear, so the grid sees one smooth, well-behaved load instead of the peaks and valleys of individual components. Rather than disconnecting during a fluctuation, the batteries absorb excess power or dispatch it to servers, tracking the grid within milliseconds. The company said it is installing 3 gigawatts of the systems across four data center campuses.

Regulators are moving in the same direction. Federal and state authorities are studying rules to better manage sudden demand drops from data centers and crypto miners, and in Texas, grid operator ERCOT plans to require large loads to “ride through” disruptions rather than dropping offline, de Azevedo said.

A Near Miss With a Warning Attached

“Within minutes of the incident occurring, our system operations team was able to stabilize the situation and return to normal operating conditions,” Dominion Energy said. PJM, for its part, reported no impact to the grid’s overall reliability. Still, the episode showed how an ordinary equipment fault can now ripple into a regional voltage event, simply because so much synchronized, self-protective computing load now sits in one place. The warning signs, as de Azevedo put it, are already flashing.

Tags:

AI InfrastructureData CentersGrid ReliabilityNorthern VirginiaPJM Interconnection

Share

An open 3.5 inch hard disk drive with the top cover removed, showing the spinning platter, read/write head, and actuator arm
Previous Post

How to Partition, Format, and Mount a New Disk in Linux With fdisk and parted

Close-up of an InfiniBand network switch with multiple cables connected, representing the network layer a Capsule Server proxies and caches for distributed RHEL fleets
Next Post

Red Hat’s Satellite Capsule Server Turns RHEL Fleet Growth Into a Bandwidth Math Problem

No Comment! Be the first one.

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

Latest
28 Oct
How to Run Zero-Downtime Schema Migrations on PostgreSQL 18 and Block Unsafe ALTER TABLE Statements With a Python Lint Gate
28 Oct
The Angular 2 Rewrite Turns a Migration Lesson Into a Security Bill: AngularJS Still Draws 533,480 Downloads a Week, and 10 Advisories Have No Open-Source Fix
Trending
October 28, 2026
How to Run Zero-Downtime Schema Migrations on PostgreSQL 18 and Block Unsafe ALTER TABLE Statements With a Python Lint Gate
October 28, 2026
The Angular 2 Rewrite Turns a Migration Lesson Into a Security Bill: AngularJS Still Draws 533,480 Downloads a Week, and 10 Advisories Have No Open-Source Fix
October 28, 2026
WordPress 7.1.4 Closes an Unauthenticated Race in Its Own Update Routine, but 19 Older Branches Had No Backport Hours After Release
October 28, 2026
How to Compress Time-Series Metrics in Python With Gorilla Delta-of-Delta and XOR Encoding
October 28, 2026
NIST’s Final Post-Quantum Transition Report Puts Every Quantum-Vulnerable Public-Key Scheme on One 2030 and 2035 Clock, and Three Federal Documents Word the Deadline Three Ways
October 28, 2026
Honeypots Recorded Probes Against Oracle E-Business Suite CVE-2026-101767 Seven Days After Its Patch, and the Finder’s Write-Up Is Dated Patch Day

Related Posts

Blue-lit server racks in a modern data center, illustrating the compute infrastructure behind the AI boom.
Articles

The AI Boom Is Spending Real Money Before Proving Real Returns

June 7, 2026
Rows of server racks in a data center representing network infrastructure targeted by botnets
News

C0XMO Botnet Shows Why Old Router Firmware Still Matters

June 7, 2026
Close-up of a USB flash drive, representing physical data-theft risk in office security incidents
News

Fake IT Support Is Now Walking Through the Front Door

June 7, 2026
A phone security app on a smartphone resting on a laptop keyboard.
News

Everest Forms Pro Flaw Is Being Exploited to Create Rogue WordPress Admins

June 7, 2026
SXZ.io SXZ.io
  • [email protected]

Categories

Articles
Learning Hub
News

All Rights Reserved by SXZ.io ©2026